A view of Lindenhurst

Grand Ave Construction Update 4/4/19

Contact Us

2301 East Sand Lake Road
Lindenhurst, IL 60046
Get Directions

  • Phone: (847) 356-8252
  • Staff Directory

Berger Construction is completing tree removal, water main and sanitary sewer relocations along Grand Ave. that should be completed by April 8.  The next step is to activate the temporary signals located at the intersections of Grand Ave. and Munn Rd., Lindenhurst/Granada Rd. and Sand Lake Rd. The temporary signals should be activated on Monday April 8. The first stage of traffic control is scheduled to occur Wednesday April 10th.  This phase of construction will close one lane of traffic in each direction.  The major work effort of stage one will be the installation of the main line storm sewer down the center of the roadway. Traffic will be shifted to the outside lanes in both directions.  Please refer to information posted on the message boards located at the east and west end of the project limits along Grand Ave. as well as at Sand Lake Rd. east of Grand Ave.