|
CALL TO
ORDER:
Mayor Betustak called the Special Meeting of the Village Board to
order at 7:00 p.m.
ROLL CALL:
ROLL CALL:
Roll call showed those present were: Mayor Betustak, Trustees:
Czyzewicz, Messmer, Norlin, Wayne and Zerba. Also in attendance
were Administrator Stevens, Attorney Phillips, Engineer Welsh,
Treasurer Neubauer and Clerk Bauschke. Trustee McCarthy was absent.
The President of Lindenhurst Sanitary District, Art Campbell then
reconvened the Lindenhurst Sanitary District’s previous meeting.
Treasurer Art Neubauer, and Clerk Sheldon Halterman were present.
Also in attendance was Robert A. Bate, P.E. of Strand Associates,
Inc.
PLEDGE OF ALLEGIANCE:
NEW BUSINESS:
DISCUSSION: SEWER AND WATER UTILITY PLANT AND INFRASTRUCTURE
IMPROVEMENTS
* WASTEWATER TREATMENT FACILITY – Village Engineer Wes Welsh
referred the Board to the “Infrastructure Improvements 6 page
Summary” that was prepared for the Special Meeting of the Village
Board and was dated January 23, 2007. (Please see attached
document.)
Engineer Welsh presented this topic. Wastewater Treatment Plant
construction is expensive and is also time consuming. It’s
approximately a 3-year lead-time to bring improvements from design
through construction to operation. Engineer Robert A. Bate of
Strand Associates, Inc. also gave a brief presentation. General
discussion occurred.
Engineer Welsh reported that Village Staff recommends that the
Lindenhurst Village Board request that the Lindenhurst Sanitary
District undertake an expansion of the Wastewater Treatment Facility
(WWTF).
Sanitary District and Village Staff recommends that the Lindenhurst
Sanitary District Trustees authorize Strand Associates to commence
the IEPA project approval and low interest loan process by
authorizing Strand Associates, Inc. to prepare a Facilities Plan and
to commence the design process for expansion of the Wastewater
Treatment Facility.
MOTION:
A motion to request that the Lindenhurst Sanitary District undertake
an expansion of the Wastewater Treatment Facility and authorize
Strand Associates, Inc. to commence the IEPA project approval and
low interest loan process by authorizing Strand Associates, Inc. to
prepare a Facilities
Plan and to commence the design process for expansion of the
Wastewater Treatment Facility was made by Trustee Norlin and 2nd by
Trustee Wayne.
ON ROLL CALL THE VOTE WAS:
AYES-5 Trustees Czyzewicz, Messmer, Norlin, Wayne and Zerba
Nays-0
Absent-1 Trustee McCarthy
Mayor Betustak declared the motion carried.
General discussion occurred. Bob Bate of Strand Associates, Inc.
referred to Table 7.03 PROJECT IMPLEMENTATION SCHEDULE that was in
tonight’s Board packet. Bob Bate broke the schedule into three
sections.
Lindenhurst Approval of Study; Prepare Facilities Plan; Facilities
Plan Submitted to IEPA; Preliminary Environmental Impacts
Determination from IEPA; Notice of Public Hearing Issued; Hold
Public Hearing through Receipt of IEPA-Facilities Plan Approval and
$45,000.00 is the proposed cost.
The following are considered “Design Related Services” for a
preliminary not to exceed cost of $456,000.00: Authorize Design
Related Services; Submit Pre-application for IEPA Revolving Loan
Assistance; Construction Drawings and Specifications to IEPA; Submit
Loan Application to IEPA; Submit Preliminary User Charge System to
IEPA; Lindenhurst Authorizes Bidding and Construction Related
Services; IEPA Approval of Drawings and Specifications; Receive IEPA
Loan Commitment Letter through Advertise for Bids.
Lastly, Open Bids; Revise User Charge System; Receive IEPA Loan
Agreement; Issue Notice to Proceed to Contractor; Project
Substantial Completion; Complete Training and O&M Documents through
Project Final Completion are considered “Construction Related
Services.”
Sanitary District Clerk Sheldon Halterman made a motion to engage
Strand Associates, Inc. to prepare the Facilities Plan for the
Wastewater Treatment Plant at a cost not to exceed $45,000.00 with
an option for the Design and Construction Related Services and
authorized this on the basis of a Professional Service Contract with
Strand Associates, Inc. upon approval of the Sanitary District
Attorney; it was 2nd by Treasurer Neubauer. President Campbell took
the Lindenhurst Sanitary District Roll Call and the motion passed.
President Campbell adjourned the Lindenhurst Sanitary District’s
meeting at 8:10 p.m. Mayor Betustak announced the Village’s Special
Meeting would continue on.
* ROUTE 45 PUMP STATION AND INTERCEPTOR SEWER-CAPACITY ANALYSIS –
Engineer Welsh reported this for information purposes only. He
presented the background on this item.
Staff recommended no action be taken at this time. Both the
southeast interceptor sewer and the Route 45 pump station, with
three of the four possible, pumps installed, have sufficient
capacity for all future development in the southeast interceptor
sewer service area if development proceeds within the parameters of
our current land use plan.
* GRAND AVENUE SEWER PUMP STATION – Engineer Welsh briefly
presented the background. This pump station is located on Grand
Ave. across from Victory Lakes and is the last pump station the
Village has that uses non-submersible pumps. A Study on this pump
station completed in 2005 advised upgrading. To relocate this above
ground station farther away from Grand Avenue land would be needed
due to the pump station was built on an easement. General
discussion occurred.
Engineer Welsh recommended the Village acquire the additional land
necessary to locate a new generator / control building further away
from Grand Avenue and proceed with design and reconstruction of the
pump station using the submersible pump alternative.
Trustee Zerba was excused and left the meeting at 8:30 p.m.
* GRAND AVENUE WATER MAIN REPLACEMENT – Engineer Welsh reported
this existing water main along Grand Avenue is located between
Prospect Drive and Grand Circle. The issue is the need to replace a
50 year old 6” diameter cast iron pipe with a 12” water main.
Options were discussed.
Village Staff recommended proceeding with design which starts with
getting need an Engineering Services Agreement from Strand and
Associates, Inc. and having Treasurer Neubauer and our financing
consultants research financing options.
* WELL NO. 11, WELL HOUSE NO. 7, STORAGE TANK NO. 3 – Engineer
Welsh reported a study was done in 2005 which concluded the
following:
1.
That a deficit of 172 gallons per minute, based upon maximum
day plus fire demand, already exists in our water supply system and
that this shortfall would grow to 1200 gallons per minute by the
year 2010.
2.
That a new deep well (Well No. 11) producing 1,200 gallons
per minute be designed and constructed in 2007.
3.
That a new well house (Well House No. 7) be designed and
constructed immediately upon completion of the deep well.
4.
That a new 400,000-gallon water storage tank and booster pump
station be designed and constructed sometime between 2010 and 2015.
Engineer Welsh mentioned the best place for the ground storage tank
was in the southeast region of the Village by Falling Waters.
5.
The location for the new well, well house and storage tank
have not yet been identified.
6.
This study accounted fro the fact that there are hundreds of
Village residents who draw their water from private wells.
Engineer Welsh stated the older wells in the Village are beginning
to decline and we are always looking for our next source of water.
Staff recommended proceeding with design and construction of a deep
well and well house while Staff works with Treasurer Neubauer and
our financial consultant to research financing options in concert
with the Grand Avenue Water Main Replacement listed above.
* LAKE MICHIGAN WATER STUDY – Engineer Welsh said this topic was
presented for informational purposes only. In 2006 the Northern
Lake County Michigan Water Planning Group was formed and Lindenhurst
joined. This planning Group is financing a feasibility study with
regard to bringing Lake Michigan water to each of the agencies
represented. The study is due to be completed by April 2007.
Discussion included if a Lake Michigan water project comes into
being how it will affect our existing water supply and distribution
system and our continued planning efforts.
Mayor Betustak thanked Engineer Welsh and Staff for such a thorough
presentation and opened the floor for Public Participation.
PUBLIC PARTICIPATION:
Stephen Baceynski, 2326 E. Grand Avenue, Lindenhurst
asked if the new proposed water main on Grand Avenue would be east
of the Village Hall? Engineer Welsh answered yes, it would be 7,520
lineal feet long between Prospect Drive and Grand Circle.
ADJOURNMENT:
A motion to adjourn the Special Village Board meeting was made by
Trustee Wayne and 2nd by Trustee Messmer.
Upon voice vote, the motion carried. Adjournment was at 9:23 p.m. |